Vestas wins a 68 MW order for a wind project in Estonia

The order includes the supply, installation and commissioning of 15 V150-4.5 MW wind turbines, as well as a 20-year Active Output Management 5000 (AOM 5000) service agreement.

“We are honored to continue the partnership with Dirkhof to deliver this project to Aidu,” says Juan Furones, Vice President of Sales for Northern and Central Europe at Vestas. “Aidu will contribute to further decarbonizing Estonia and we are proud to support this project with our industry-leading wind power solutions.”

The site is located in Lüganuse parish, Ida-Viru county, in the north-eastern part of Estonia.

Delivery and installation of the wind turbines is expected to occur in the third quarter of 2023 with commissioning scheduled for the first quarter of 2024.