Wind energy will provide at least 12 % of European electricity by 2020

In Europe, in 2010, five countries sourced more than 10 % of their electricity from wind farm and wind energy will provide at least 12 % of European electricity by 2020, therefore signifi cantly contributing to the 20/20/20 goals of the European energy and climate policy.

The kinetic energy of the wind is transformed into mechanical energy by the rotors of wind turbines and then into electricity that is injected into the grid. Wind speed is the most important factor affecting wind turbine performance because the power that can be extracted from the wind is proportional to the cube of the wind speed, e.g. an increase in the long-term mean wind speed from, for example, 6 to 10 m/s (67 %), causes a 134 % increase in production [EWEA, 2009].

Wind speed varies depending on the season, location, orography and surface obstacles and generally increases with height, creating the wind shear profile. Surface obstacles, such as forests and buildings, decrease the wind speed, which accelerates on the windward side of hills and slows down in valleys. Annual variations up to 20 % are normal.

A wind turbine starts to capture energy at cut-in speeds of around 3 m/s (11 km/h) and the energy extracted increases roughly proportionately to reach the turbine rated power at about 12 m/s (43 km/h), remaining constant until strong winds put at risk its mechanical stability, thereby forcing the wind turbine to stop at cut-out speeds of around 25 m/s (90 km/h).

Once stopped and secured wind turbines are designed to withstand high wind speeds of above 60 m/s (216 km/h). Generally, utility-scale wind farm plants require minimum average wind speeds of 6 m/s. There are two main market sectors: onshore and off shore wind energy. The differences include complication of installation, working environment (saline and tougher at sea) and facility of access for installation and maintenance.

In addition, as the wind is stronger and more stable at sea, wind turbine electricity production is higher offshore. Current onshore wind
energy technology certainly has room for further improvement, e.g. locating in forests and facing extreme weather conditions, yet it is a mature technology.

Offshore wind power, however, still faces many challenges. There is a third sector, small wind turbines (up to 10 kW) for niche applications such as isolated dwellings, but this sector is unlikely to provide a significant share of the European electricity supply.

At the end of the last century, a wind turbine design (the three-bladed, horizontal-axis rotor) arose as the most cost-effective and efficient. The main technological characteristics of this design are: an upwind rotor with high blade and rotor efficiency, low acoustic noise, appropriate tip speed; active wind-speed pitch regulation; variable rotor speed with either a gearbox connected to a medium- or high-speed generator or direct rotor connection to a low-speed generator; and concrete, steel or mix towers.

An alternative design around a rotor with a vertical axis, e.g. Vertiwind [Technip] and Aerogenerator X,1 is meant to have key advantages in particular for offshore wind farms. The equipment is placed just above sea level which enormously facilitates installation and maintenance. However wind turbines based on this concept are yet to be built commercially.

The main driver for developing wind technology is to minimise the cost of energy (CoE) production, for which efforts focus on minimising capital costs and maximising reliability. These drivers translate into: design adapted to the wind characteristics; grid compatibility; aerodynamic performance; and adaptation for offshore. Technical considerations that cover several of these goals include windturbine weight reduction; larger rotors and advanced composite engineering leading to higher yields; and design for off shore installation, operation and maintenance.

Throughout the years the electricity grid codes in the EU-27 Member States (MS) have became stricter and now require that wind turbines highly support the grid by having, for example, fault ride-through capabilities, as well as a high-quality electricity output. The consequence is the evolution of wind turbine technology -as reflected by wind turbine configuration- from the initial machines’ fixed rotor speed with stall control (type A) through minimal variable-speed drive introducing pitch control (type B), then the doubly-fed induction generator (DFIG, type C) allowing higher variable speed configuration, and type D which allows the rotor to freely adapt its speed to the wind (thus maximising energy uptake) while using full power electronics converters, to provide the best-quality electricity
to the grid. The added market share of the last two configurations has increased from 44 % of installed capacity in 2000 to 84 % in 2009 [Llorente Iglesias et al., 2011].

The production of the magnetic field in wind turbine electricity generators is the object of another key technological evolution, from electromagnets to permanent magnets. The former included simple squirrel-cage (SCIG) and then wound-rotor (WRIG) induction generators, then compact DFIG and fullsize, low-speed electromagnet generators (LSEMG) in a wind turbine without a gearbox. New designs are substituting electromagnets with permanent magnets (PMG) on the grounds of increased reliability, higher partial-load effi ciency, and more flexibility of integration with compact gearboxes or power electronics.

However, this change is not without problems because of supply/demand unbalances of the basic raw materials needed for permanent magnets (rare earth elements) which lately have triggered escalating prices, and because the main world supplier, China, has set up tight export quotas. Last but not least, ores of rare earths are often found mixed with radioactive materials and its mining and the disposal of its waste presents additional environmental challenges.

Key issues for offshore wind power include: reducing maintenance stops; safe access for staff when the sea is rough (the technological evolution of the access vessels determines how rough a sea they can withstand and thus the number of days that they can guarantee access to turbines); improving the design of the coupling between foundation/installation vessels to reduce installation time and to increase the number of working days; cost effective foundations/installation for deeper waters and further-offshore sites; and reducing the cost of interconnection, currently about 20–25 % of the CapEx.

Interwoven with those issues is the reliability of offshore wind turbines: the more reliable they are the less access is needed for corrective maintenance. In addition, the development of floating foundations is accelerating and the first deep-water wind farm could be envisaged for 2015.

The trend towards ever larger wind turbines, which slowed in recent years, has resumed. The largest wind turbine now in commercial operation has a capacity of 7.5 MW, and most manufacturers have introduced designs of wind turbines in the 4.5 – 10 MW range (up to a total of 42 different designs) mostly for offshore use.

The recently presented large wind turbines, whilst 10 MW designs have been presented by Sway (Norway), Clipper (US) and AMSC Windtec (US-AT). Both industry and academia see even larger wind turbines (10 – 20 MW) as the future of offshore machines [TPWind, 2010].

Rotor diameters which, in general stabilised since 2004 at around 100 m, have, during the last two years, started to grow again and nowadays a significant number of wind turbine designs include rotors greater than 110 m. For rotor sizes between, for example, 115-120 m diameter, a very wide range of wind turbine electrical capacity from 2 to 6.5 MW is offered. The main reasons are commercial and the adaptation to local wind conditions.

Tip speed is limited by acoustic noise and wind turbines might be requested to operate at reduced speed in noise-sensitive areas. However, offshore, the tip speed can increase to above 80 m/s thus increasing electricity production. Pitch control is the technology of choice for controlling rotor speed, coupled with variable-speed regulation. Drive trains tend to reduce their weight and offshore wind turbines tend to stabilise hub heights at 80 – 100 m. This is because offshore wind power shear is lower and there is a trade-off between taller towers yielding slightly higher production but needing heavier, increased foundation loads involving higher tower and foundation costs [EWEA, 2009]. Offshore foundations for deeper waters (30-60m) are expected to diversify away from monopile steel into multi-member (jackets, tripods) and innovative designs such as tribucket, twisted jacket, suction bucket monopile and even concretebased structures [CT, 2011].

The cost of wind energy depends on the cost of raw materials; technology fundamentals; supply bottlenecks (e.g. limited competition in offshore cable supply); market supply/demand balance; administrative barriers (permit process etc., including those caused by NIMBYism); payments for wind electricity, e.g. feed-in tariff s (FiT), FiT premium, market + premium, competitive tender, cash grant, etc.; and on risks and uncertainties impacting on the investors and lenders.

Up to 2004, wind turbine prices declined, influenced by technology learning and the increasing volumes of production. Supply/demand imbalances and the increase of raw material and component pr ices pushed up onshore wind turbine prices to around €1150/kW in 2009, when the reduction in raw materials costs caused by the financial crisis, manufacturing over capacity and increasing competition pushed down prices to around €950/kW by mid-2011, with the Spanish and Italian markets showing the lowest prices [BNEF, 2011b].

Beyond Europe, the US at €790/kW (at 1 EUR = 1.4 USD) and China at €438/kW (at 1 EUR =9.2 CNY) showed lower prices [BNEF, 2011a, 2011b]. Price quotes include transport to the site but not installation. The high price of wind turbines did not turn into high profits for their manufacturers, as European wind turbine manufacturers published 2010 EBIT in the range of 4-7 %, whilst Chinese ones did much better at 14-16 % [BNEF, 2011a].

Offshore windturbine prices are in the range of €1500/kW [MML, 2011]. Similarly, European capital investment (CapEx) for onshore wind farm projects showed a reduction to €1 000/kW in 2003/4, and then climbed to reach its peak in 2008, then down to around €1 250/kW in 2010 [EU,2011]. In the USA, the DoE suggests for a CapEx level around €1 600/kW [DoE, 2011]. Offshore CapEx have been even more aff ected by supply-chain limitations and the difficulties of working offshore, and showed strong price increases from €2 200/kW in 2007 to €3 000–4 200/kW in 2011 with the upper end covered by farther off shore, deep-water wind farms [JRC].

MML [2011] suggests that raw material costs are not that significant but instead prices of offshore wind power include a market premium in the order of 20 %. This is notably higher than for onshore wind due to significant risks related to both construction and operation.

Onshore operation and maintenance (O&M) costs are estimated at €21/MWh (or €47/kW/yr at a 25% capacity factor) and, over a 20-year operation period, constitute 35–45 % of total costs. They have presented a declining trend from the €35/MWh for the old 55 kW wind turbines [EWEA, 2009]. Offshore O&M costs are in the €25-40/MWh (or €106/kW/yr at a 40% capacity factor) range with a European average of €30/MWh [EU, 2011] and towards the upper range for farther off shore installations.2

The cause of these high costs is mainly the high fixed cost of getting access to the wind turbines, even when the higher production partly compensates for the difference. Offshore insurance costs, on top of O&M, can be as high as €5–12/MWh.2

The technology learning effect is presented in terms of a wind turbine-cost progress ratio (PR), and a PR of 90% caused cost reductions up to 2003 [NEEDS, 2006; Junginger, 2007], but then this learning effect was overcome by market factors causing prices to
increase. It is very difficult to estimate the technology learning effect in offshore technology because market and project aspects (e.g. farther offshore wind farms) have had a much higher influence in wind turbine prices and project costs. Offshore wind power experienced a period of fierce competition (2000 -2004) which reflected in neutral PR and, since 2005, a PR above 100 % showed the continuous increase of capital costs [GH, 2009] in what can be seen as negating technology learning.

During the last six years, offshore technology R&D has focused on increasing the reliability of wind turbines which brought about an increase in capital cost – although the cost of energy benefi ted from the increased reliability.2

The expected capital investment trend is for onshore capital costs to reduce further due to non-technological factors – such as the entry into the competition of Chinese wind turbine suppliers and the increasing size of wind turbine blades – playing a significant role, and then to stabilise. Without doubt technology will continue to progress but, as wind turbines are viewed as some kind of commodity, it is likely that non-technological factors will have a stronger infl uence in the onshore turbine price.

Offshore wind power is expected to maintain high costs until 2015 but it has more room for factors including technology improvements (e.g. to reduce foundation and installation costs), learning-by-doing, improved supply chain and more competition which could lead to a reduction of 28 % by 2020 [MML, 2011].

The integration of wind energy into the electricity grid can occasionally involve other costs including the reinforcement of grids, the need for additional balancing power and ancillary services. The first two items have been evaluated in Denmark, per MWh of wind electricity, at €0.1–5 (for 30 % wind share) and €1–4 (20 % wind share), respectively [Krohn et al., 2009]. A range of studies in the US shows that costs for wind energy integration of up to 40 % are below €7.5/MWh, and often below  €3.8/MWh [DoE, 2011].

These costs can be reduced through creating larger balancing areas, reducing the wholesale market gate-closure times to 4 – 6 hours, more frequent intra-day markets, intra-hour scheduling (e.g. 5-minute scheduling) and better forecasting used by system operators. There is also room for low-cost improvement by optimising the grid operational procedures [DoE, 2011].

Curtailment is a problem of increasing impact. Curtailment is the forced stopping of wind electricity generation following instructions from grid operators. This happens mostly in two cases, either there is excess (overall) electricity production compared to the existing demand (e.g. on a windy Saturday night), or the local wind power generation is larger than what can be absorbed by the transmission lines to the centres of demand.

Curtailment is not regularly quantified in Europe, and it is expected to remain limited, but elsewhere curtailment is having a strong impact: 17 % in Texas in 2009 reduced to 8 % in 2010 after a new line was built [DoE, 2011], as well as 17 % in Inner Mongolia in China [CCBIS, 2011].

The discussion on costs of generating wind energy often overlooks the fact that this energy is sold in wholesale markets where all electricity negotiated receives the price conceded to the marginal supplier, i.e. the most expensive supplier accepted to generate. In this context, zero-fuelcost technologies, such as wind, displace fueldependent,
expensive technologies and therefore
reduce the marginal price applied to all electricity
traded (and not just for wind power). In periods of
high fossil fuel prices, the resulting multiplying
eff ect overcompensates for any subsidy that wind
might receive. Calculations in Denmark quantifi ed
the related savings, over the period 2004 – 2007, at
an average of €3.3/MWh of traded electricity. This
fi gure, due to a 20 % wind share, is equivalent to
a saving of €16.5/MWh for (only) wind-generated
electricity [Krohn et al., 2009]. These benefi ts do
not take into account the increased security of
supply, reduction in price volatility and the oil-GDP
eff ect, nor the cost of purchasing carbon under the
European Trading Scheme.
The system availability of European onshore wind
turbines is above 97 %, among the best of the
electricity generation technologies [EWEA, 2009],
although because malfunctions occur most when
the wind is blowing strong this 3 % unavailability
translates into a higher lost production of maybe
5 %.2 The typical capacity factors onshore are 1 800
– 2 200 full-load hours equivalent (in which a wind
turbine produces at full capacity), and 3 000 – 3 800
off shore, for a European global average of 1 960
hours.3 Technology progress tends to increase
these fi gures but best sites onshore have already
been taken and new wind farms are built at lower
wind speed sites.
1.3. Market and industry status and
potential
The global installed wind capacity grew at a 29 %
annual average between 2000 and 2009, and added
39.4 GW in 2010 to total 199 GW (+24.7 %) [BTM,
2011]. The off shore sector grew by 52 % in 2010 to
1 100 MW [JRC], including shoreline and intertidal
installations, although it still contributes no more
than 1.6 % of global installed capacity. In the
EU-27, wind installations increased 9.3 GW to reach
84.3 GW (+12.4 %) [GWEC, 2011], and off shore made
up 11 % of these new installations. With an annual
increase of 18.9 GW, China moved to fi rst place in the
ranking of cumulative installed capacity at 44.7 GW
[CWEA, 2011a], ahead of the US which installed
5.11 GW for a cumulative 40.2 GW. However, in terms
of operational, i.e. grid-connected capacity, the
US is still the world leader as it was estimated
that around 34 % of Chinese installed capacity
(15 GW) was not connected to the grid at the end
of 2010 [ChinaDaily, 2011]. The status of the EU as
the major world market is now part of history since
2004, when 70 % of newly installed capacity took
place in the EU, this fi gure was reduced to 24 %
over the succeeding six years. During 2010 wind
installations accounted for 16.7 % of new electricity
plant in the EU [EWEA, 2011] and 25 % in the US
[DoE, 2011].
Consequently with this trend, top European turbine
manufacturers suff ered a reduction of their global
market share from 67 % in 2007 [EWEA, 2009] to 40 %
in 2010 [BTM-JRC, 2011], a trend that will continue
this year as Chinese manufacturers continue to
take advantage of their stronger market. The Top-
10 manufacturers in 2010 included four Chinese
(Sinovel, Goldwind, Dongfang and United Power),
Vestas and Siemens (DK), Gamesa (ES), Enercon
(DE), GE Wind (US) and Suzlon (IN).

In the EU-27 in 2010, the
wind energy generation,
e s t imated at the
European average of
21.2 % load factor, was
148 TWh or 4.5 % of the
estimated 3 300 TWh of
EU electricity demand.
Wor l dwi d e wi n d
supplied 357 TWh.3
The countries with the
highest wind share in
the electricity mix in
2010 included Denmark
(22 %), Portugal (17.1 %),
Spain (16.6 %), Ireland
(10 %) and Germany
(6.2 %).3 The integration
of 50 % wind power into
an electricity system
is seen as technically
possible [EA, 2007].
Achieving the 2020 EU industry target of 230 GW, of
which 40 GW is off shore, remains a realistic scenario.
Electricity production would be 520 TWh, between
13 and 15 % of EU electricity demand [EWEA, 2011].3
The 2030 potential is 350 GW, of which 150 GW
offshore, and would produce 880 TWh, between
21 and 24 % of EU demand.3 The economically
competitive potential of 12 200 TWh by 2020 and
30 400 TWh by 2030 [EEA, 2009] is beyond reach. In
the EU, in the long run, off shore wind should reach
50 % of wind installed capacity.
According to the International Energy Agency, global
onshore cumulative capacity could reach 670 GW
by 2020, of which 109 GW is off shore, with 215 GW
in China and 115 GW in the US. By 2030 global
installed capacity could reach 1 024 GW of which
194 GW off shore, 270 GW in China, and 210 in the
US, and generate 7 % of the then estimated world
consumption of 32 700 TWh [IEA, 2010a, 2010b].
Wind is already competitive with fossil-fuel
generation in high-wind sites such as Scotland. The
expected rise in fossil fuel prices, along with wind
technology improvements – fuelled by initiatives such
as the SET-Plan [European Commission, 2007] – will
make that at more and more sites, wind generates
cheaper electricity than fossil fuels. Wind power is
thus an insurance against fl uctuating (and rising)
energy prices in addition to creating security of
supply and protection against unstable sources of
fossil fuels.

Barriers to large-scale deployment
The main barriers preventing wind energy development
have not changed much since the 2009 Technology
Map [JRC, 2009], namely: a high-levelised cost of
electricity (CoE) caused mainly by high capital
costs and, especially offshore, high O&M costs;
administrative barriers (lengthy permit process,
etc.), social acceptance (often after individual visual
perceptions mixed up with the NIMBY syndrome) or
the lack of trained, experienced staff , in particular
for the expected offshore development in the
2014 – 2020 period.
The group of economic barriers include: relatively high
raw material (steel, concrete, copper, rare earths),
component and turbine prices; low competition
among second- and third-tier suppliers (drive
shaft, brakes, drive-train bearings, etc.); high gridconnection
costs; limited grid transmission capability
that is reinforced only slowly; scarcer sites with good
resources and, since the fi nancial crisis, very tight
financing conditions. Higher wind penetration is
also prevented by lack of adequate interconnections,
including international links, which are necessary
also for the easing of balancing requirements that
would be the result of a larger balancing area [EWEA,
2009]. Financing issues have somehow eased during
2011 in that there are now more institutional actors
(e.g. pension funds) ready to fi nance debt. However,
the fi nancial stakeholders expect high internal rate
of returns (IRR) for off shore wind which is causing
a further increase in CoE, this high premium could
be reduced through clear and long-term policy
commitments as well as a structured eff ort to reduce
risks and barriers faced by investors.2

Entry barriers to offshore wind have eased with
regards to wind turbines, even if there are still only
two clear market leaders, as nearly all manufacturers
have commercialised or presented off shore turbines.
Entry barriers remain for cabling manufacture though
(HVAC/HVDC subsea cables), with few actors able
to manufacture cable connections to the onshore
grid, and – to a lesser extent – cable-laying and
foundation-installation vessels.
Onshore grid expansion plans are disappointing
[European Commission, 2011a]. In 2010, ENTSO-E
prepared a pilot ten-year network development plan
under the assumption of only a 25 % renewable
energy penetration by 2020, when even the National
Renewable Energy Action plans estimate more than
37 %. One of the greatest challenges remains the
connection (both on- and off shore) of the very large
off shore potential.
Finally, the group of administrative barriers include
lengthy procedures, too many authorities involved,
inexperienced civil servants, non-homogenous
application of regulations, and an unclear
administrative framework, among others [European
Commission, 2011a].
1.5. RD&D priorities and current
initiatives
The engine behind European RD&D is the European
Wind Initiative (EWI) of the SET-Plan, composed
of industry, EU Member States and the European
Commission. The EWI has an estimated investment
of EUR 6 billion shared between industry and
public funding. Its steering group has approved
the following R&D priorities suggested by the Wind
Technology Platform [TPWind, 2010]: new turbines
and components for on- and off shore deployment,
large turbines, testing facilities; development and
testing of new off shore foundations, and its massmanufacturing;
grid integration including longdistance
HVDCs, connections off shore to at least
two countries and multi-terminal solutions; and
resource assessment including a new European wind
atlas and spatial planning instruments. While R&D
programmes run by the European Commission are
already adapting to these priorities, Member States
are expected as well to align their R&D funding in
the near future.
Public bodies could possibly have the largest impact
in cost reduction if they focused in reducing the risks
and uncertainties existing in the diff erent phases of
a wind farm project. Examples include identifying and reducing the uncertainty of wind energy yield
calculations (which would result in lower risks for
fi nancial institutions providing debt); and reducing
the risks of the permit process, e.g. through
streamlining the permit schemes, public planning
of preferred wind deployment areas, etc. Identifying
why fi nancial institutions require such a high IRR for
off shore wind and subsequently taking action would
help to ease the pressure on off shore CoE.
Wind energy depends on other sectors including:
the electricity grid which is a fundamental enabler
for higher wind penetration and is currently
underdeveloped in particular regarding international
interconnections; electricity storage (pumped or
reservoir hydropower, compressed air, etc.); and
manufacture of subsea HVAC/HVDC cables. The
European installed capacity of hydro-pumping
storage, currently at 40 GW, should be increased
in order to allow for more system fl exibility. More
reservoir-hydro capacity would contribute to grid
support and this would enable more wind and other
non-fi rm renewables into the system.
The European society is still not aware of the full
extent of the climate change problem and of the
impact of wind energy to alleviate this problem.
There is a need for the EU and individual Member
States to raise awareness that reduce the “not in my
back yard” syndrome toward wind farms and their
required grid connections. Last but not least, there
is a need for better cooperation among the European
wind industry, academia and R&D institutions in
research, education and training.
RD&D in advanced materials off ers synergies with a
number of low-carbon industries (non-exhaustive):
fi bre-reinforced composites with the nuclear and
solar energy; coatings with the solar power, biomass
and electricity storage industries; special concretes
with building and nuclear; high-temperature
superconductors with the electricity transmission
and storage sectors, etc. [European Commission,
2011b].
Synergies exist between the offshore sector and
the oil and gas (O&G) industry in areas such as the
manufacture of installation vessels. This sector can
bring in experience and know-how to the off shore
wind sector, in particular on substructure installations
and on operation and maintenance issues.
Some ocean energy projects share grid-related
issues with off shore wind and even with onshore
at a lower level. Exchange of technological knowhow
with the aeronautics industry might result from the entry of EADS in the wind sector. Other sectors
that have possible synergies with wind are the grid
components, in particular for off shore installations,
and electricity storage sectors. The latter, along
with the auto industry for electric cars, and with
the support of smart grids/metering, would create
a demand-management scenario able to adapt and
assimilate surplus wind electricity.

References
Bloomberg New Energy Finance (BNEF), 2011a. Wind market outlook Q2 2011, 18.07.11.
Bloomberg New Energy Finance (BNEF), 2011b. Wind turbine price index, issue V, 27.07.11.
BTM Consult, 2011. World Market Update 2010, March 2011.
BTM-JRC, 2011. Basic data from [BTM, 2011] has been updated e.g. to disaggregate fi gures
for REpower turbines from its mother company (Suzlon), and to include smaller European
manufacturers.
China Daily USA, 2011. 16.04.11: China grids to connect 90 m kW of wind power by 2015.
Consulted 6/8/11 at http://www.chinadaily.com.cn/bizchina/2011-04/16/content 12338 443.htm
CCB International Securities Ltd. (CCBIS), 2011. China Wind Power, 4.04.11. This report quantifi es
the amount of curtailed (“not procured”) wind electricity in the Inner Mongolia province at
2.1 TWh for H1 of 2010.
Chinese Wind Energy Association (CWEA), 2011a. Chinese wind market data 2010.
Personal communication, May 2011.
Energy Analyses (EA), 2007. 50 % Wind Power in Denmark in 2025 (English Summary), July 2007.
European Environmental Agency (EEA), 2009. Europe’s onshore and off shore wind energy
potential, 2009.
European Commission, 2007. Communication from the Commission to the Council, the
European Parliament, the European Economic and Social Committee and the Committee of
the Regions – A European strategic energy technology plan (SET-plan)-Towards a low carbon
future, COM/2007/723. Available from http://ec.europa.eu/ energy/ techn ology/ set_plan/
set_plan_en.htm
European Commission, 2011a. SEC (2011) 130 fi nal – Recent progress in developing renewable
energy sources and technical evaluation of the use of biofuels and other renewable fuels in
transport in accordance with Article 3 of Directive 2001/77/EC and Article 4(2) of Directive
2003/30/EC, and accompanying staff working documents. Brussels, 31.1.2011.
European Commission, 2011b. On-going work of the groups of experts on the SET Plan Materials
Initiative, unpublished.
European Union (EU), 2011. On-going work of the Team of the European Wind Industrial Initiative,
made up by representatives of the Member States and the European Commission.
European Wind Energy Association (EWEA), 2009a. Wind Energy-the Facts. Part I-technology;
Part III-economics; Part IV-industry and markets; Part V-environmental impact; Part VIscenarios
and targets.
European Wind Energy Association (EWEA), 2011. Wind in power: 2010 European statistics, 2011.
European Wind Technology Platform (TPWind), 2010. Wind European Industrial Initiative Team,
2010-2012 Implementation Plan, May 2010. Available at http://setis.ec .europa. eu/ activities/
implementation-plans/Wind_EII_Implementation_ Plan fi nal.pdf/view
Garrad Hassan (GH) for BWEA UK Off shore Wind, 2009. Charting the Right Course – Scenarios for
off shore capital costs for the next fi ve years, July 2009.

Global Wind Energy Council (GWEC), 2011. Global wind report – Annual market update 2010.
April 2011. Available at www.gwec.net
International Energy Agency (IEA), 2010a. Energy Technology Perspectives 2010.
International Energy Agency (IEA), 2010b. World Energy Outlook 2010.
Joint Research Centre (JRC) database of wind turbine characteristics and wind installations.
Joint Research Centre (JRC) of the European Commission, 2009. 2009 Technology Map of the
European Strategic Energy Technology Plan (SET-Plan). Part–I: Technology Descriptions.
Available at http://setis.ec.europa.eu/about-setis/2009-technology-map-fi nal-draft
Junginger, M., 2007. Presentation at the IEA workshop on technology learning curves.
Paris, 11- 12.06.2007.
Krohn, S., Morthorst, P-E., Awerbuch, S., 2009. The Economics of Wind Energy. EWEA 2009.
Llorente Iglesias R., Lacal Arantegui, R., Aguado Alonso, R., 2011. Power electronics evolution in
wind turbines—A market-based analysis. Renew Sustain Energy Rev (2011),
doi:10.1016/j.rser.2011.07.056.
Mott MacDonald (MML), 2011. Costs of low-carbon generation technologies. Report for the UK’s
Committee on Climate Change, May 2011.
New Energy Externalities Developments for Sustainability (NEEDS), 2006. An EC 6FP project.
Deliverable D3.3 – RS 1a, Cost development – an analysis based on experience curves, August
2006.
Off shore Wind Capital Grant Scheme (OWCGS) of the UK’s BERR. Analysis of data in the annual
reports 2005 – 2007 of several wind farms included in the scheme:
http://www.berr.gov.uk/energy/environment/etf/off shore-wind/page45496.html
Technip: Technip launches Vertiwind fl oating wind turbine project. Press release available at
http://www.technip.com/en/press/technip-launches-vertiwind-fl oating-wind-turbine-project
The Carbon Trust of the UK (CT), 2011. Presentation on the foundations competition which left four
innovative designs for the next phase of testing: MBD’s suction bucket monopile; Keystone’s
twisted jacket; Giff ord/BMT/Freyssinet gravity structure; and SPT Off shore/Wood Group’s
tribucket design.
US Department of Energy (DoE), 2011. 2010 Wind Technologies Market Report, Lawrence Berkeley
National Laboratory, August 2011.