The National Transmission and Despatch Company Limited (NTDCL) of Pakistan signed three agreements for 129.5 MW from Jhimpir wind farm.

 

The plan calls for Tapal Wind Energy to build a 30 MW facility, Master Wind Energy to install a 49.5 MW plant and Gul Ahmed Wind Power construct an additional 50 MW wind park.

The PPAs have received the green light from NTDCL authorities and all three wind power producers will close their financing till 31 March 2015. The farm will start production by the end 2016.

NTDC, incorporated in 1998 operates and maintains twelve 500 KV and twenty nine 220 KV Grid Stations, 5077 km of 500 KV transmission line and 7359 km of 220 KV transmission line in Pakistan.

The main functions of NTDCL are categorized as central power purchasing agency, system operator, transmission network operator, contract registrar and power exchange administrator for the energy portfolio of Pakistan.

As a Central Power Purchasing Agency (CPPA), the utility works on procurement of power from GENCOs, Hydel & IPPs on behalf of Distribution Companies (DISCOS) for delivery through 500 kV, 220 kV and 132kV Network.

Current projects undertaken by NTDCL include D. G Khan 500 kV sub -station and transmission line, New Okara 220 kV Sub-Station Transmission Line and Dispersal of Power from Jarwar IPP Jarwar – Sadiqabad 132 kV Double Circuit Transmission Line.

The Jhimpir Wind Power Plant is a wind farm located at Jhimpir in Thatta District of Sindh province in Pakistan, 120 kilometres North-East of Karachi.

The project has been developed by Zorlu Energy Pakistan at a total cost of $143 million.

Recently, Pakistan Meteorological Department has conducted a detailed Wind Power Potential Survey of Coastal Areas of Pakistan.

This study finds that Sindh coastal areas have greater wind power potential than Balochistan coastal areas. Potential areas cover 9700 sq.km in Sindh.

In Pakistan, first wind power generation plant of 50 MW was inaugurated in December 2012 and started full production in 2013. The wind power potential in Pakistan that has been identified in Sindh and Balochistan is more than 50,000 MW while Punjab has potential of producing almost 1,000 MW.