Vestas receives 117 MW wind power order for the first utility-scale wind farm to be built in Jordan

The project consists of 38 V112-3.0 MW wind turbines which will be installed about 180 km south of Amman, in the Tafila region, Jordan.

Delivery of the wind turbines will start in the second quarter of 2014, and the wind power plant is expected to be commissioned in the second quarter of 2015.

The contract for the Al Tafila wind power plant includes supply, installation and commissioning of the wind turbines, civil and electrical works, a VestasOnline